PMP Formulas Cheat Sheet: Every Formula You Need
Complete PMP formulas reference covering EVM, PERT, communication channels, and all calculations tested on the PMP certification exam.
Do You Really Need to Know Formulas for the PMP Exam?
Yes, but with an important caveat. The current PMP exam is not a math test. You will not face dozens of calculation questions. However, you can expect several questions that require formula knowledge — and these are essentially free points if you have prepared. Unlike situational questions where judgment is required, calculation questions have objectively correct answers. Know the formula, do the math, get the point.
This guide covers every formula that may appear on the PMP exam, organized by knowledge area. Bookmark this page and review it regularly during your preparation.
Earned Value Management (EVM) Formulas
EVM is the most formula-heavy topic on the exam. Master these in order:
Base Measurements
- Planned Value (PV): The authorized budget for scheduled work at a given point in time
- Earned Value (EV): The value of work actually completed, measured against the baseline
- Actual Cost (AC): The total cost incurred for work performed
- Budget at Completion (BAC): The total authorized budget for the project
Variance Formulas
- Cost Variance (CV) = EV - AC — Positive means under budget
- Schedule Variance (SV) = EV - PV — Positive means ahead of schedule
Performance Indices
- Cost Performance Index (CPI) = EV / AC — Greater than 1.0 means under budget
- Schedule Performance Index (SPI) = EV / PV — Greater than 1.0 means ahead of schedule
Memory trick: For variances, EV always comes first. For indices, EV is always the numerator.
Forecasting Formulas
- Estimate at Completion (EAC) = BAC / CPI — Current cost performance continues
- EAC = AC + (BAC - EV) — Remaining work at original rate
- EAC = AC + [(BAC - EV) / (CPI x SPI)] — Both cost and schedule performance considered
- Estimate to Complete (ETC) = EAC - AC — How much more will be spent
- Variance at Completion (VAC) = BAC - EAC — Expected budget variance at the end
To-Complete Performance Index (TCPI)
- TCPI (to meet BAC) = (BAC - EV) / (BAC - AC)
- TCPI (to meet EAC) = (BAC - EV) / (EAC - AC)
TCPI greater than 1.0 means you need to perform better than planned on remaining work. Greater than 1.0 is harder to achieve.
Estimating Formulas
Three-Point Estimates
- PERT (Beta Distribution): (O + 4M + P) / 6 — Weighted toward the most likely estimate
- Triangular Distribution: (O + M + P) / 3 — Equal weight to all three estimates
- Standard Deviation (sigma): (P - O) / 6
- Variance: [(P - O) / 6]^2 — Standard deviation squared
Where O = optimistic, M = most likely, P = pessimistic.
Communication Formula
Communication Channels = n(n-1) / 2
Where n = number of people including the project manager. When a person is added, the number of new channels equals the old total of people.
Procurement Formulas
Point of Total Assumption (PTA)
Used with Fixed Price Incentive Fee contracts:
PTA = [(Ceiling Price - Target Price) / Buyer's Share Ratio] + Target Cost
The PTA is the cost point where the seller bears all additional cost overruns because the ceiling price has been effectively reached.
Schedule Formulas
- Total Float = Late Start - Early Start (or Late Finish - Early Finish)
- Free Float = Early Start of successor - Early Finish of current activity - 1
Study Strategy for Formulas
Create a formula sheet from memory before each practice exam. Repeat until you can write all formulas from recall in under five minutes. On exam day, use the first few minutes to write down your formulas on the scratch paper provided. This reduces anxiety and frees mental energy for the scenarios. For a printable version, visit our cheat sheets page, and practice formula-based questions on our exam simulator.
Practice what you just learned
Test your knowledge with flashcards, mini exams, and full-length practice tests on PMPprep.
Start Studying Free