PMP Formulas Cheat Sheet

All PMP exam formulas in one place — EVM, PERT, communication channels, EMV, and more.

All PMP Formulas

Estimating

FormulaPurpose
PERT = (O + 4M + P) / 6Three-point estimate (weighted average)
σ = (P − O) / 6Standard deviation of a single activity
Variance = σ²Variance of a single activity
Project σ = √(Σ variances)Standard deviation of the project (critical path)

Communication

FormulaPurpose
Channels = n(n−1) / 2Number of communication channels for n stakeholders

Risk

FormulaPurpose
EMV = Probability × ImpactExpected Monetary Value (decision tree analysis)

Financial

FormulaPurpose
ROI = (Net Profit / Cost) × 100Return on Investment
NPV = Σ [Cash Flow / (1+r)^t]Net Present Value (higher = better)
BCR = Benefits / CostsBenefit-Cost Ratio (must be > 1.0)
PV = FV / (1+r)^nPresent Value of future money

Procurement

FormulaPurpose
PTA = [(Ceiling − Target Price) / Buyer Share] + Target CostPoint of Total Assumption (FPIF contracts)

Agile

FormulaPurpose
Velocity = Story Points / SprintTeam throughput per iteration
Sprints Remaining = Points Left / VelocityRelease forecasting