Critical Path Method (CPM) Deep Dive

Complete guide to the Critical Path Method for the PMP exam — forward pass, backward pass, float calculation, and compression.

Critical Path Method

The Critical Path Method (CPM) is a scheduling technique that identifies the longest path through the project network diagram. This path determines the shortest possible project duration.

Key Concepts

  • Activities on the critical path have zero total float — any delay to these activities delays the entire project
  • A project can have multiple critical paths (which increases risk)
  • The critical path can change as the project progresses
  • Schedule compression techniques (crashing, fast tracking) only work on critical path activities

Forward Pass (Calculate ES and EF)

  • ES (Early Start) — Earliest an activity can begin
  • EF (Early Finish) = ES + Duration
  • Start from the beginning; at merge points, take the largest EF

Backward Pass (Calculate LS and LF)

  • LF (Late Finish) — Latest an activity can finish without delaying the project
  • LS (Late Start) = LF − Duration
  • Start from the end; at burst points, take the smallest LS

Float Calculations

  • Total Float = LS − ES = LF − EF — How much an activity can be delayed without delaying the project end date
  • Free Float = ES(successor) − EF(current) — How much an activity can be delayed without delaying the next activity
  • Zero total float = critical path activity