Work Breakdown Structure (WBS) Deep Dive

Complete guide to creating and using the WBS for the PMP exam — decomposition rules, 100% rule, and WBS dictionary.

Work Breakdown Structure

The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

Key WBS Rules

  • 100% Rule — The WBS must capture 100% of the work defined by the project scope, including project management work
  • The lowest level of the WBS is the work package
  • Work packages should be decomposed to a level where they can be estimated, scheduled, and monitored
  • The WBS is deliverable-oriented, not activity-oriented
  • The WBS defines scope — if it's not in the WBS, it's not in the project

WBS Components

  • Level 1 — Project name
  • Level 2 — Major deliverables or phases
  • Level 3+ — Sub-deliverables, broken down further
  • Work Package — Lowest level, the basis for estimating and managing

WBS Dictionary

A companion document that provides detailed information for each WBS element:

  • Description of work
  • Responsible organization
  • Schedule milestones
  • Quality requirements
  • Cost estimates
  • Acceptance criteria
  • Technical references